The safety measures followed in design and execution of turnkey electrical projects :
- Implementation of safety procedures as per safety manual for plant requirements during erection and commissioning of electrical installation.
- Training and increasing awareness within employees about safety standards.
Name of project
Locations
- Complete Erection testing commissioning of 145kv Sub-station at Vacmet Ltd Indore
- Revamping of 6.6KV 1250KW MG set-8nos at two Substation with LT and HT Control and switching Panel at Naval Dockyard Mumbai
- Revamping of 145 KV substation at Mukand Steel Ltd Navi Mumbai
- Revamping of 145KV substation at Torrent power Ahmadabad
- Revamping of 145kv substation at Mahindra Sanyo Specialty steel Ltd Mumbai
- Revamping of 145kv substation at Reliance IDC Mauda Nagpur
- Replacement of 220kv breaker at MAHAGENCO BHIRA Raigad
- Retrofitting of Generator protection relay at MAHAGENCO URAN Mumbai
- Retrofitting of feeder protection relay at Supreme Petrochem Ltd Raigad
- Turnkey Project – Electrification of 40KM line HT and LT line with 667 Consumer. Client MSEDCL dhule Dhule
- ETC on Turnkey basis for Electrical and Instrumentation Fuel Farm Expansion Bengaluru Airport Project Banglore
- Supply and Retrofitting of 11KV MOCB, VCB of ABB, Jyoti, CGL make With New VCB at BMC Mumbai
- Supply, Erection, Testing & Commissioning of 6.6KV VCB panels at Ordinance Factory Mumbai
- Supply, Erection, Testing & Commissioning of 11KV VCB Panels at Ordinance Factor. pune
- Supply, Erection, Testing &Commissioning of 33KV VCB indoor Panels at Dhansmruti Textile ltd Solapur
Basic Engineering activities
- Document control Index.
- Design Basis
- Sizing calculation
- Load flow and short circuit study on ETAP.
- Switchyard equipments
- Transformer (Power / Distribution / Lighting)
- Switchyard structure (Out sourced)
- Cables (Voltage drop & short circuit )
- Capacitor
- DG sizing
- DC system
- Lighting
Earthing based on soil resistivity report.
- Earth mat calculation for switchyard.
- Earthing grid calculation for plant.
- Lightning protection calculation
- Single line diagram.
- Typical control scheme with DCS/ PLC Interface.
- Technical specification and Data sheet.
- QAP for bought out equipments.
- Vendor drawing review/ Approval.
- Electrical IO List.
- Relay co-ordination
Field engineering activities
- Cable schedule.
- Cable termination schedule.
- Layout drawing.
- Equipment layout for Electrical Rooms.
- Switchyard layout drawing.
- Earthing and Lightning Protection layout drawing.
- Cable Layout drawing.
Erection & Commissioning activities
- Establishment of Site Office
- Erection Schedule
- Verification of Material received at site.
- Mobilization of man power
- Positioning of equipments.
- Cable Tray Erection
- Earthing & Lightning Protection
- Cable laying
- Cable termination
- Statutory approvals
- Load trials
- Preparation of as built drawings.
- Handing over of plant